- Role
- Project manager
- When
- August to October 2026
- Status
- Finished
- Aim
- Faster changeovers and less money wasted on over-ordering stock
- Did
- Planning, buying, invoices, strip-out and rebuild
The job
A disorganised supplies and laundry space that needed to work harder. I cleared it, redesigned it and rebuilt it so changeovers run faster and stock is no longer over-ordered.
- Planned the new layout with the operations manager, so the space works for the people using it.
- Took out the old storage and disposed of the waste.
- Bought the shelving, boxes and fittings, and managed the invoices.
- Built and rebuilt the room so all of the stock fits and can be seen at a glance.
Before and after






Done for the owners of Ditchling Cabin, where I have worked as part-time operations manager since 2018.